Concrete Basin for cooling tower, supports and foundations, equipment steel framing supports for SOCAR chemical plant (Sumqayit - Azerbaijan) - 2012
![]() | ![]() |
---|---|
![]() | ![]() |
![]() | ![]() |
Concrete basin for water at the base of FRP cooling tower; building for control room, different foundations for pumps and filters and concrete frames to support crane. Calculation according to Eurocodes. Seismic analysis in zone 4 for ACI 318 and UBC1997.
Analysis for cracking joints and waterstops.
In a second time calculation of steel frames and support for filters and other equipments. Calculation according to Eurocodes 3 and 8. Limit for deformations.
Visit of the site for meeting with the Customer.
Customer: Hamon Thermal Europe - France